Boiler installation at a Primary School

This was an installation at Orchard Primary School in Hounslow where we installed 2 x Hamworthy Purewells Variheat 180 boilers with a combined output of 360KW, we piped these up to a large 200mm diameter low loss header and installed new 3” pipe work in between with all new pumps, control valves and other associated equipment including a new Trend BMS panel complete with sensors and all necessary safety interlocks.